BHC RHODES is working with the City of Raymore to plan improvements to North Madison to meet the City’s standards for traffic capacity, safety, and neighborhood amenities.
Current Project Activity:
Preliminary design has been completed and a project walk-thru with City staff has been done. BHC RHODES will now:
- Coordinate with local utility companies with facilities along North Madison to relocate any lines that would be impacted during construction.
- Prepare final plans for bidding and construction.
- Identify any easements or additional R/W that may be required during construction.
Project Schedule:
Here are a list of the major remaining project milestones and estimated dates:
| Submittal of Final Plans and Specifications to City | August 25, 2008 |
| Bid opening | September 30, 2008 |
| Council Readings on Award of Contract | October 13 & 27, 2008 |
| Construction Startup | November 2008 |
| Project Completion | June 2009 |
Updated May 29, 2008
|